The short answer
Calculating irrigation comes down to four questions:
- How much water do the plants need? Estimate it from evapotranspiration (ET), a plant or crop factor, and the area.
- How much should you actually apply? Divide by the system’s efficiency.
- How fast does your system apply water? This is the application or precipitation rate.
- How long and how often should you run it? Divide the amount needed by the rate, and space the cycles by how much water your soil holds.
The steps below give the formulas for each, with examples for drip and sprinklers.
Step 1: How much water do the plants need?
Plant water use is usually estimated from reference evapotranspiration (ETo), the water lost from a standard grass surface on a given day. Many weather services, irrigation districts and extension services publish daily or average ETo. To adjust for your plants, multiply by a crop coefficient (Kc) or plant factor:
Water need (inches/day) = ETo × Kc
Gallons per day = ETo (in/day) × Kc × area (sq ft) × 0.623
The factor 0.623 converts one inch of water over one square foot into gallons.
Metric: 1 mm over 1 m² is 1 litre, so
Litres per day = ETo (mm/day) × Kc × area (m²)
Typical plant factors vary. Actively growing vegetables at full size are often around 1.0, cool-season lawns are commonly treated as fairly high, and established drought-tolerant shrubs much lower. Local extension guides often publish factors suited to your region and plant types.
Example: a 200 sq ft vegetable bed, ETo 0.2 in/day, Kc 1.0: 0.2 × 1.0 × 200 × 0.623 ≈ 25 gallons/day (net).
Step 2: Account for efficiency (net vs. gross)
No system delivers every drop to the roots. Divide the net need by efficiency to get the gross amount to apply:
Gross = net ÷ efficiency
Common planning assumptions are around 0.85–0.9 for a well-built drip system and lower for sprinklers. For the bed above with drip at 0.9, that’s 25 ÷ 0.9 ≈ 28 gallons/day. For the background, see what is the efficiency of drip irrigation.
Step 3: How fast does your system apply water?
Drip application rate
For evenly spaced emitters in a grid or rows:
Application rate (in/hr) = 231 × emitter GPH ÷ (emitter spacing in inches × row spacing in inches)
Example: 1 GPH emitters at 12-inch spacing in rows 18 inches apart: 231 × 1 ÷ (12 × 18) ≈ 1.07 in/hr.
For drip, it’s often simpler to skip inches and work in gallons. Add up the zone’s flow (number of emitters × GPH) and divide gallons needed by that. Our guide on how to calculate drip rate covers measuring actual emitter output.
Sprinkler precipitation rate
For sprinklers, the standard formula is:
Precipitation rate (in/hr) = 96.3 × total GPM ÷ area (sq ft)
Example: a zone flowing 8 GPM over 1,200 sq ft: 96.3 × 8 ÷ 1,200 ≈ 0.64 in/hr.
The total GPM and area should belong to the same zone. Manufacturers also publish precipitation rates for nozzles at given spacings.
Step 4: How long to run
Run time (hours) = inches needed ÷ application rate (in/hr)
or, for drip:
Run time (hours) = gallons needed ÷ zone flow (GPH)
Example (drip): 28 gallons ÷ zone flow of 40 GPH = 0.7 hours ≈ 42 minutes. Example (sprinkler): 0.25 inch ÷ 0.64 in/hr ≈ 0.39 hours ≈ 23 minutes.
If water starts running off before the run time is up, which is common with sprinklers on clay or slopes, split it into shorter cycles with a soak period between them.
Step 5: How often to water
How often depends on how much water the root zone can hold. Soils hold very roughly 0.5–1 inch of plant-available water per foot of depth in sands, and more, roughly 1.5–2.5 inches per foot, in loams and many clays. Exact values vary. Gardeners commonly water when about half of the available water has been used.
Days between watering ≈ (available water per foot × root depth in feet × 0.5) ÷ daily water use
Example: loam holding about 2 in/ft, 1-ft root zone, 0.25 in/day use: (2 × 1 × 0.5) ÷ 0.25 = every 4 days, applying about 1 inch (before efficiency) each time.
Shallow-rooted plants and sandy soils need more frequent, smaller waterings. Deep-rooted shrubs and trees in loam or clay can go longer between deeper waterings.
Step 6: Check flow, water use and cost
- Supply flow (bucket test): gallons ÷ seconds × 60 = GPM. Make sure each zone’s flow fits within it, with a margin (see how to size a drip irrigation system).
- Water used per cycle: GPM × minutes, or GPH × hours.
- Cost: water used × your price per unit. Bills are often in cubic meters, hundred cubic feet (CCF; 1 CCF ≈ 748 gallons) or thousands of gallons.
Handy conversions
| From | To |
|---|---|
| 1 inch over 1 sq ft | 0.623 gallons |
| 1 inch over 1,000 sq ft | about 623 gallons |
| 1 mm over 1 m² | 1 litre |
| 1 gallon | 3.785 litres; 231 cubic inches |
| 1 GPM | 60 GPH |
| 1 GPH | about 3.785 L/h |
| 1 cubic meter | about 264 gallons |
Treat the numbers as a starting point
ET-based calculations are estimates. Local conditions such as wind, shade, reflected heat, soil variation and plant size all shift actual needs. Use the math to set initial run times, then check soil moisture a few inches down a day after watering and adjust. Revisit schedules as the season changes, since summer ET can be several times higher than spring or autumn ET.